24/7 Emergency Response Active Parkland County · Edmonton · Alberta-wide

Capability

Turnarounds that finish inside the window. Every time.

Planned and emergency shutdown support — scoped, scheduled, crewed, pre-staged, and closed out inside the window you committed to. When a unit is offline, every day has a number attached to it. KBIM's job is to make that number smaller.

Overview

When the unit goes offline, the clock starts. We make it stop sooner.

A day of lost production at a 350 MW generating unit is worth mid-six-figures. At a major upgrader, seven. A turnaround that slips by a week isn't an inconvenience — it's the worst financial event of the operating year. KBIM plans around that math.

KBIM has been running turnaround and shutdown scopes across Alberta's heaviest industry for nearly fifty years. Primary gearbox rebuilds in aggregate plants. Full mechanical scopes on cogeneration facilities. Life-extension shutdowns on 350 MW power units. SAGD plant turnarounds. Pulp-mill outages. Upgrader maintenance windows. The scope is different every time. The discipline isn't.

Every turnaround runs on the same playbook: over-plan, over-staff, pre-stage everything, and treat the schedule as a contract — not a projection. We can be booked into a shutdown window 12–24 months out with a committed crew size, scope, and finish date. Tooling, rigging, fabricated spools, and consumables are pre-staged in the laydown yard before the window opens. When scope expands mid-window (and on a real unit, it always does), we extend crew to hold the end-date — we don't push the completion date to accommodate an added find.

One phone number through the planning cycle. One crew through the window. One close-out package through the hand-back. One accountable contractor for the millwright scope, the fabrication, the mechanical work, and — if you want it — the project management wrapped around all of it. On time. On spec. Through the window.

What's included

A single contractor. The full turnaround scope.

Six disciplines that show up on almost every shutdown. All under one roof, one contract, one accountable point of failure — not five vendors finger-pointing when the schedule slips.

Turnaround planning

Scope development, work-package build, schedule modelling, resource loading, and pre-turnaround readiness reviews. Everything the window needs, decided before the window opens.

Work packsPrimaveraReadiness

Mechanical & millwright scope

The core KBIM execution scope: rotating equipment overhauls, alignment, gearbox rebuilds, pump & motor work, conveyor drive rebuilds, and every millwright discipline the turnaround calls for.

Red SealDocumentedOEM spec

Fabrication & pressure piping

Pipe spools fabricated to ASME code, structural modifications, skid builds, replacement chutes and hoppers — all pre-built in the shop, pre-tested, and delivered ready to rig in.

Pre-fabB-PressureHydro tested

Rigging & heavy lift

Engineered lift plans, certified riggers, hydraulic gantries, skidding & jacking, and critical-lift coordination for the heaviest pieces in the plant.

EngineeredCertifiedCritical lift

Portable machining on-site

Line boring, flange facing, on-unit grinding, journal repair, and the on-deck machine work that would otherwise mean pulling the asset and shipping it out of province.

Line boringFlange facingOn-unit

Commissioning & start-up

Witnessed reassembly, alignment confirmation, hydrostatic & pressure testing, system flushes, baseline vibration & thermal, and supported start-up through first-fire / first-run.

WitnessedBaselineSupported

How we work

Four phases. One window. Zero slipped schedules.

A turnaround doesn't start when the unit comes offline. It starts 12–24 months before, in a planning room. By the time the window opens, every scope, every tool, every lift is already decided.

  1. 1

    Scope & pre-plan

    Walk-downs, work-pack development, schedule modelling, resource loading, long-lead parts ordered, engineering commissioned. All of it dated against the window opening.

  2. 2

    Pre-stage

    Tooling, rigging, fabricated spools, consumables, replacement components — staged in the laydown yard, tagged to work packs, verified against the plan. Nothing shows up on day one.

  3. 3

    Execute

    Unit isolated, crew on-deck, scope running on plan. Daily schedule reviews, scope-change protocol ready for the inevitable finds, extra crew on standby — because holding the end-date is non-negotiable.

  4. 4

    Commission & hand-back

    Reassembly witnessed, alignment confirmed, pressure tests signed, start-up supported, and the close-out package — every measurement, every sign-off, every deviation — handed to your reliability team.

Scale & capacity

What a committed turnaround crew looks like.

The difference between a shutdown that holds its schedule and one that slips is what shows up in the laydown yard the morning the window opens. Here's what we bring.

70+ millwright peak

Red Seal · rotation-ready

Fleet of service trucks

Mobile shops · welding · parts

Hydraulic gantries

To 100-ton · engineered lifts

Portable machining fleet

Line boring · flange facing

In-shop fab capacity

20-ton crane · pre-built spools

Laser alignment kits

Pruftechnik · SKF · to 0.0005"

Vibration & thermal

Baseline + as-left capture

Laydown & work-pack

Tagged · verified · ready

Proof of work

The 51-day turnaround that rewrote the worst-case scenario.

A 350 MW generating unit came into a major life-extension shutdown with an original outage estimate pushing past two months of worst-case. KBIM was handed the scope. The crew delivered the unit back to the operator in 51 days — two full weeks ahead of worst-case — with zero lost-time incidents and every inspection signed off on the first walk.

01 — Scope

350 MW life-extension.

Full mechanical scope across a 350-megawatt generating unit with turbine, generator, boiler-feed, and cooling-tower work inside a single shutdown window.

02 — Crew

70 millwrights at peak.

Crew size ramped to 70+ ticketed millwrights at peak execution, running day & night shifts across multiple concurrent scopes to hold the end-date.

03 — Result

14 days ahead of worst-case.

Unit handed back to the operator 14 days ahead of the worst-case plan — an estimated $13.4M of avoided-downtime upside vs. the originally-planned outage duration.

04 — Safety

Zero lost-time incidents.

70 crew · multi-shift · 51 days · zero LTIs. Every JSA reviewed, every lock-out verified, every lift engineered — safety record matched the production record.

05 — Inspection

First-walk sign-off.

Every critical inspection — alignment, weld quality, torque records, pressure tests — signed off on the first walk. No rework. No re-open. No schedule hit.

06 — Playbook

The playbook goes out on every call.

Representative figures — every turnaround is different. But the playbook that got this one back early is the same one that goes out on every window we run.

Safety & compliance

Schedule matters. Safety holds.

A turnaround is the highest-risk operating environment an industrial plant sees all year — multiple trades, concurrent scopes, energy-isolated equipment, critical lifts, and a compressed schedule pushing everyone to move faster. This is where cutting corners kills people. KBIM's non-negotiable rule: the only acceptable finish is the one where everyone walks off the site.

  • Site-specific JSAs for every work pack, reviewed daily
  • Lock-out / tag-out by the millwright doing the work
  • Engineered lift plans for every critical or over-tonnage lift
  • Dedicated on-site safety lead on every major turnaround
  • Red Seal journeymen only on precision and critical work
  • Daily close-out meetings — schedule, safety, scope-changes

COR

Certificate of Recognition

ISNetworld

Contractor prequalified

ComplyWorks

Audit & compliance

Avetta

Supply chain verified

WCB AB

Good standing

Red Seal

Journeymen only

Frequently asked

What turnaround managers want to know before the commit.

How far in advance do we need to book?
Major turnarounds — anything with a meaningful crew size and a fixed window — we book 12 to 24 months out. That gives us time to lock the crew, engineer the lifts, order long-lead parts, pre-fabricate spools and structural, and run a proper readiness review before the window opens. Shorter-cycle planned outages (2–4 weeks) we typically book 6–12 months out. Emergency / unplanned shutdowns we mobilize inside hours.
Can you commit to a firm finish date?
Yes — and we back the commitment with crew capacity, not caveats. When we commit to a window, the scope, the peak crew size, and the end-date are all in the contract. If scope expands mid-window, we extend crew to hold the end-date — we don't push the completion date to cover an added find. The 51-day, $13.4M-upside turnaround on our proof-of-work band was exactly this model.
Do you handle turnaround planning, or just execution?
Both. Our planning team develops work packs, builds Primavera schedules, runs resource-loading models, and leads pre-turnaround readiness reviews — either as a stand-alone planning engagement 12+ months out, or rolled into the execution contract. For operators with in-house turnaround planning groups, we run execution-only and integrate with your existing plan.
How big a crew can you mobilize?
Peak turnaround crew of 70+ ticketed millwrights for a single site, plus supporting fabrication, rigging, and mechanical disciplines. For operators running multiple concurrent sites during a corporate-wide maintenance season, we schedule across multiple windows — but a single site at peak typically tops out around 70–80 on the deck, which is the size our coordination and safety models are built around.
What happens when scope expands mid-window?
Every turnaround expands. A unit comes apart, something looks worse than the walk-down suggested, a new scope drops in. Our scope-change protocol is formal: written change order, impact assessment (crew, schedule, cost), decision from the operator, and — if the change affects the end-date — a crew extension plan on the same day. The end-date holds unless you decide otherwise. You never find out at the hand-back that the window slipped.
Can you deliver a turnkey close-out package?
Yes. Every turnaround ships with a formal close-out package: scope-as-executed summary, measurements (as-found and as-left), alignment reports, weld procedures and welder logs, torque records, pressure test certificates, NDE reports, photos, deviation log, and a written recommendation for the next outage cycle. For operators under asset-integrity management systems, we format the package to match your document control standard (PDF, Excel, or direct CMMS upload).